[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101469":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101469,779,1,"单选题","监理人征得发包人同意后，应在开工日期（ ）向承包人发出开工通知。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3天前",false,{"key":16,"text":17,"correct":18},"B","7天前",true,{"key":20,"text":21,"correct":14},"C","10天前",{"key":23,"text":24,"correct":14},"D","14天前","知识点:监理人的职责。监理人征得发包人同意后，应在开工日期7天前向承包人发出开工通知。2020版教材P98。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]