[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101467":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101467,779,1,"单选题","为了明确划分由于政策法规变化或市场物价浮动对合同价格影响的责任，《标准施工合同》中的通用条款规定的基准日期是指（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","投标截止日前第14天",false,{"key":16,"text":17,"correct":14},"B","投标截止日后第14天",{"key":19,"text":20,"correct":21},"C","投标截止日前第28天",true,{"key":23,"text":24,"correct":14},"D","投标截止日后第28天","知识点:订立合同时需要明确的内容。通用条款规定的基准日期指投标截止日前第28天。2020版教材P93。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]