[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101460":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101460,779,1,"单选题","某工程项目现场有甲、乙两个承包人同时施工。由于监理人的错误指示与协调能力不足，选成甲承包人受到乙承包人的干扰被迫暂停施工。关于甲承包人停工损失处理方式的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","自行负责",false,{"key":16,"text":17,"correct":14},"B","由发包人给予补偿，合同工期不予顺延",{"key":19,"text":20,"correct":14},"C","不予补偿，但应合理顺延合同工期",{"key":22,"text":23,"correct":24},"D","由发包人给予补偿，合同工期相应顺延",true,"知识点:施工合同管理有关各方的职责。监理人指示延误或指示错误以及未完成现场协调工作，均由发包人负责赔偿。2020版教材P92。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]