[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101455":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101455,779,1,"单选题","根据九部委发布的标准设计合同，发包人应提前（ ）向设计人发出开始设计通知。因发包人原因造成合同签订之日起（ ）内未能发出开始设计通知的，设计人有权提出价格调整要求，或者解除合同。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7天，60天",false,{"key":16,"text":17,"correct":18},"B","7天，90天",true,{"key":20,"text":21,"correct":14},"C","14天，60天",{"key":23,"text":24,"correct":14},"D","14天，90天","知识点:设计工作中重要的时间规定。符合专用合同条款约定的开始设计条件的，发包人应提前7天向设计人发出开始设计通知。除专用合同条款另有约定外，因发包人原因造成合同签订之日起90天内未能发出开始设计通知的，设计人有权提出价格调整要求，或者解除合同。2020版教材P86。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]