[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101447":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1101447,779,1,"单选题","根据九部分的《标准勘察设计合同》，勘察项目负责人在情况紧急且无法与发包人取得联系时，可采取保证工程和人员生命财产安全的紧急措施，并在采取措施后（ ）内向发包人提交书面报告。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","24小时",true,{"key":16,"text":17,"correct":18},"B","48小时",false,{"key":20,"text":21,"correct":18},"C","7天",{"key":23,"text":24,"correct":18},"D","14天","知识点:勘察项目负责人的相关规定。勘察项目负责人在情况紧急且无法与发包人取得联系时，可采取保证工程和人员生命财产安全的紧急措施，并在采取措施后24小时内向发包人提交书面报告。2020版教材P79。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]