[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101444":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101444,779,1,"单选题","根据九部委的勘察合同的规定，发包人应向勘察人提供的资料不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","坐标和标高",false,{"key":16,"text":17,"correct":14},"B","建筑总平面图",{"key":19,"text":20,"correct":21},"C","初步设计",true,{"key":23,"text":24,"correct":14},"D","人防设施的资料","知识点:勘察合同中发包人提供的资料。勘察阶段不可能提交设计资料。2020版教材P77。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]