[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101439":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101439,779,1,"单选题","根据九部委发布的《标准勘察合同》，以下有关合同文件效力由大到小的排序正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同协议书-投标函及附录-中标通知书-专用条款-通用条款",false,{"key":16,"text":17,"correct":18},"B","中标通知书-专用条款-通用条款-发包人要求-勘察费用清单",true,{"key":20,"text":21,"correct":14},"C","合同协议书-通用条款-专用条款-发包人要求-勘察费用清单",{"key":23,"text":24,"correct":14},"D","专用条款-通用合同条款-发包人要求-勘察纲要-勘察费用清单","知识点:九部委勘察合同中合同文件的效力排序。合同文件的解释顺序：合同协议书、中标通知书、投标函及投标函附录、专用合同条款、通用合同条款、发包人要求、勘察费用清单、勘察纲要、其他合同文件。2020版教材P75。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]