[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101438":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101438,779,1,"单选题","根据九部委发布的《标准设计合同》，设计费用的支付说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计费用只能采用定金支付，不能采用预付款",false,{"key":16,"text":17,"correct":14},"B","由于不可抗力或设计人的原因解除合同时，定金不予退还",{"key":19,"text":20,"correct":14},"C","设计费应保留3%的质量保证金",{"key":22,"text":23,"correct":24},"D","发包人应在收到中期支付申请后的28天内支付中期款项",true,"知识点:设计合同价款的确定。选项A，可以采用定金或预付款。选项B，不可抗力或非勘察人原因，定金不予退还。选项C，勘察和设计都没有质量保证金。2020版教材P82。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]