[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101436":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101436,779,1,"单选题","根据九部委的《标准勘察设计合同》，以下有关更换勘察项目负责人的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","勘察人指派项目负责人应事先征得发包人同意",false,{"key":16,"text":17,"correct":14},"B","勘察人可以自行更换项目负责人",{"key":19,"text":20,"correct":21},"C","勘察人更换项目负责人应事先征得发包人同意",true,{"key":23,"text":24,"correct":14},"D","勘察人应在更换7前将拟更换的项目负责人的姓名和详细资料提交发包人","知识点:勘察项目负责人的相关规定。选项AB，指派项目负责人不需要征得发包人同意，但更换需要。选项D，勘察人更换项目负责人应事先征得发包人同意，并应在更换14天前将拟更换的项目负责人的姓名和详细资料提交发包人。2020版教材P78。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]