[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101424":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101424,779,1,"单选题","某工程所有人为其工程投保建筑工程一切险，工程尚未完工时，该工程所有人即于6月10日开始使用部分工程，后全部工程于9月10日完工，9月30日验收合格。保险单列明保险期终止日为6月1日。则该建筑工程一切险保险人的保险责任期限终止日为（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","6月10日",false,{"key":16,"text":17,"correct":14},"B","9月10日",{"key":19,"text":20,"correct":14},"C","9月30日",{"key":22,"text":23,"correct":24},"D","6月1日",true,"",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]