[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101410":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101410,779,1,"单选题","建筑工程一切险的保险期限( )开始。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","自工地动工",false,{"key":16,"text":17,"correct":14},"B","保险合同中约定日期",{"key":19,"text":20,"correct":14},"C","自主要材料、设备运抵工地",{"key":22,"text":23,"correct":24},"D","工地动工或用于保险工程的材料、设备运抵工地之时起，以先发生者为准",true,"2020版教材P19-22 本题考查的是工程建设涉及的主要险种。建筑工程一切险的保险责任自保险工程在工地动工或用于保险工程的材料、设备运抵工地之时起始，至工程所有人对部分或全部工程签发完工验收证书(或验收合格)或工程所有人实际占用(或使用)或接受该部分(或全部工程)之时终止，以先发生者为准 。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]