[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101292":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101292,779,1,"单选题","（2020年真题）大中型建设工程设计变更超过原设计标准或批准标准时，正确的处理方式（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","业主根据变更重新与承包商签订合同",false,{"key":16,"text":17,"correct":14},"B","承包商与设计人协商变更事项并报监理人批准",{"key":19,"text":20,"correct":21},"C","业主按照规定程序办理变更审批手续",true,{"key":23,"text":24,"correct":14},"D","设计人决定按变更后的标准或规模进行设计","P3-6 本题考查合同签订及履行阶段的管理任务和方法。 通常，合同变更应当符合下列条件： (1)变更的内容应符合合同约定或者法律法规规定。变更超过原设计标准或者批准规模时，应由当事方按照规定程序办理变更审批手续。 (2) 变更或变更异议的提出，应符合合同约定或者法律法规规定的程序和期限。 (3) 变更应经当事方或其授权人员签字或盖章后实施。 (4) 变更对合同价格及工期有影响时，相应调整合同价格和工期。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]