[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101173":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1101173,779,1,"单选题","建筑工程一切险的保险期限的开始时间为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自工地动工或材料、设备运抵工地时起，以先发生为准",true,{"key":16,"text":17,"correct":18},"B","自工地动工",false,{"key":20,"text":21,"correct":18},"C","自主要材料、设备运抵工地",{"key":23,"text":24,"correct":18},"D","保险公司中约定日期","2020版教材P20 本题考查的是建筑工程一切险。建筑工程一切险的保险责任自保险工程在工地动工或用于保险工程的材料、设备运抵工地之时起始，至工程所有人对部分或全部工程签发完工验收证书（或验收合格），或工程所有人实际占用（或使用）或接受该部分（或全部工程）之时终止，以先发生者为准。但在任何情况下，保险人承担损害赔偿义务的期限不超过保险单明细表中列明的建筑期保险终止日。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]