[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101137":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101137,779,1,"单选题","某施工合同履行中，发包人派驻施工现场的代表甲平时很少参与管理，都由发包人的员工乙对承包人完成的工程量确认并以甲的名义签字后支付工程款，但乙并未获得发包人法定代表人的书面授权。工程竣工结算时，甲对乙确认的其中几项进度款提出异议。此时，对已支付的工程款（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","经乙签字的均无效，全部由甲重新确认",false,{"key":16,"text":17,"correct":18},"B","经甲确认的有效，甲不予确认的无效",true,{"key":20,"text":21,"correct":14},"C","经乙签字的全部有效",{"key":23,"text":24,"correct":14},"D","需委托造价管理部门确定","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]