[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101091":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101091,779,1,"单选题","对于抢险救灾的工程，一般采用（ ）的计价方式。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","单价合同",false,{"key":16,"text":17,"correct":14},"B","固定总价合同",{"key":19,"text":20,"correct":14},"C","可调总价合同",{"key":22,"text":23,"correct":24},"D","成本加酬金合同",true,"本题考查的是招标采购阶段的管理任务和方法。成本加酬金合同通常适用于工程复杂，工程技术、结构方案难以预先确定，时间特别紧迫 （如抢险救灾）的项目",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]