[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101087":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1101087,779,1,"单选题","下列（）的施工项目适宜选择单价合同作为施工合同计价方式。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包时施工工程内容和工程量尚不能明确确定",true,{"key":16,"text":17,"correct":18},"B","工程设计图纸完整详细，能准确确定工程量及施工计划，施工期较短",false,{"key":20,"text":21,"correct":18},"C","工程设计图纸完整详细，能准确确定工程量及施工计划，建设周期一年半以上",{"key":23,"text":24,"correct":18},"D","工程复杂，工程技术.结构方案难以预先确定，时间特别紧迫","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]