[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101085":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101085,779,1,"单选题","以下合同计价模式下，（ ）方式中承包商所承担的风险最小。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","固定单价合同",false,{"key":16,"text":17,"correct":14},"B","可变单价合同",{"key":19,"text":20,"correct":14},"C","固定总价合同",{"key":22,"text":23,"correct":24},"D","成本加酬金合同",true,"本题考查的是合同计价方式。成本加酬金计价模式下，成本部分是据实结算的，承包商的风险最小。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]