[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101073":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101073,779,1,"单选题","FIDIC合同系列中，《施工合同条件》中，如果承包商在被要求对测量记录进行审查后（）天内未向工程师发出此类通知，则视为记录准确予以认可。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","24",{"key":23,"text":24,"correct":14},"D","48","2020版教材P153-157 如果承包商在被要求对测量记录进行审查后14 天内未向工程师发出此类通知，则视为记录准确予以认可。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]