[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101071":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101071,779,1,"单选题","FIDIC系列合同，《施工合同条件》中承包商的试验，工程师应提前至少（ ）小时将其参加试验的意向通知承包商。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","12",false,{"key":16,"text":17,"correct":14},"B","24",{"key":19,"text":20,"correct":14},"C","48",{"key":22,"text":23,"correct":24},"D","72",true,"2020版教材P153-157 工程师应提前至少72小时将其参加试验的意向通知承包商。如果工程师未在商定的时间和地点参加试验，除非工程师另有指令，承包商可自行进行试验，并视为是在工程师在场的情况下进行的。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]