[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101070":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101070,779,1,"单选题","英国NEC合同文本中规定，（ ）都可以提出召开早期警告会议，并在对方同意后邀请其他方出席。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目经理和分包商",false,{"key":16,"text":17,"correct":18},"B","项目经理和承包商",true,{"key":20,"text":21,"correct":14},"C","承包商和公用事业部门",{"key":23,"text":24,"correct":14},"D","分包商和地方行政机关代表","2020版教材P163-164 项目经理和承包商都可以提出召开早期警告会议，每一方都可在对方同意后要求其他人员出席该会议。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]