[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101056":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101056,779,1,"单选题","根据美国AIA标准合同文本，以下有关CM合同的论述，正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","CM承包商可以赚取总包、分包合同的差价",false,{"key":16,"text":17,"correct":18},"B","风险型CM合同一般采用成本加酬金的计价方式",true,{"key":20,"text":21,"correct":14},"C","CM承包商可以负责设计工作",{"key":23,"text":24,"correct":14},"D","CM承包商对雇主委托范围的工作，必须全部由分包商实施","2020版教材P165-166 风险型 CM 合同采用成本加酬金的计价方式，成本部分由业主承担， CM 承包商获取约定的酬金。 CM 承包商签订的每一个分包合同均对业主公开，业主可以参与分包合同的谈判，业主按分包合同约定的价格支付， CM 承包商不赚取总包与分包合同之间的差价。CM 承包商在工程设计阶段就应介入，为设计者提供建议；CM 承包商对业主委托范围的工作，可以自己承担部分施工任务，也可以全部由分包商实施。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]