[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101055":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101055,779,1,"单选题","根据NEC《工程施工合同》，对于签订合同时价格已经确定的合同属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","目标合同",false,{"key":16,"text":17,"correct":18},"B","标价合同",true,{"key":20,"text":21,"correct":14},"C","管理合同",{"key":23,"text":24,"correct":14},"D","成本补偿合同","本题考查的是ECC合同中的内容组成。标价合同适用于签订合同时价格已经确定的合同；目标合同适用于拟建工程范围在订立合同时还未完全界定或预测风险较大的情况，承包商的投标价作为合同的目标成本，当工程费用超支或节省时，雇主与承包商按合同约定方式分摊；成本补偿合同，适用于工程范围界定尚不明确，甚至以目标合同为基础也不够充分。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]