[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101054":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101054,779,1,"单选题","一份施工合同采用了英国NEC合同文本，其中的主要选项条款为选项 E，则下列（ ）论述正确。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","该合同是固定总价合同",false,{"key":16,"text":17,"correct":14},"B","承包商的投标价作为目标成本",{"key":19,"text":20,"correct":21},"C","工程成本部分实报实销，按合同约定的工程成本一定百分比作为承包商的收入",true,{"key":23,"text":24,"correct":14},"D","该合同的乙方，可与若干施工分包商订立分包合同，确定的分包合同履行费用由雇主支付","本题考查的是ECC合同中的内容组成。主要选项条款为E，即为成本补偿合同。成本补偿合同的特点是工程成本部分实报实销，按合同约定的工程成本一定百分比作为承包商的收入",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]