[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101052":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1101052,779,1,"单选题","根据ECC合同，发生了非承包商的过失原因而引起的事件，需要核算补偿，若变更由承包商提供的工程信息，则该补偿事件的影响按对（ ）最有利的解释进行计价。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","业主",true,{"key":16,"text":17,"correct":18},"B","承包商",false,{"key":20,"text":21,"correct":18},"C","工程师",{"key":23,"text":24,"correct":18},"D","善意第三方","本题考查的是ECC合同中的合作伙伴管理理念。在补偿事件中，若变更由承包商提供的工程信息，则按对业主最有利的解释计价。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]