[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101047":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101047,779,1,"单选题","ECC合同，项目经理应在早期警告会议上对所研究的建议和做出的决定记录在案，并将记录发给（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","雇主",false,{"key":16,"text":17,"correct":18},"B","承包商",true,{"key":20,"text":21,"correct":14},"C","分包商",{"key":23,"text":24,"correct":14},"D","工程师","2020版教材P163-164 项目经理应在早期警告会议上对所研究的建议和做出的决定记录在案，并将记录发给承包商。因此，本题的正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]