[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101044":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101044,779,1,"单选题","按ECC合同文本，关于主要选项条款的说法，下列不正确的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","选项A：带有分项工程表的标价合同",false,{"key":16,"text":17,"correct":14},"B","选项B：带有工程量清单的标价合同",{"key":19,"text":20,"correct":21},"C","选项C：带有分项工程表的标价合同",true,{"key":23,"text":24,"correct":14},"D","选项D：带有工程量清单的目标合同","2020版教材P162 选项 A: 带有分项工程表的标价合同;选项 B: 带有工程量清单的标价合同;选项 C: 带有分项工程表的目标合同;选项 D: 带有工程量清单的目标合同;",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]