[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101039":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101039,779,1,"单选题","银皮书规定，当原定进度计划与实际进度不相符时，承包商还应提交一份修订的进度计划，除非业主在收到进度计划后的（）天内向承包商发出通知，指出其不符合合同要求。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":21},"C","21",true,{"key":23,"text":24,"correct":14},"D","28","2020版教材P158-161 当原定进度计划与实际进度不相符时，承包商还应提交一份修订的进度计划，除非业主在收到进度计划后的21 天内向承包商发出通知，指出其不符合合同要求，承包商即应按照该进度计划进行工作，业主人员有权依照该进度计划安排其活动。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]