[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101033":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101033,779,1,"单选题","在接收证书颁发前业主确实使用的工程，视为自（ ）起已被业主接收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","开工之日",false,{"key":16,"text":17,"correct":18},"B","开始使用之日",true,{"key":20,"text":21,"correct":14},"C","缺陷责任期结束之日",{"key":23,"text":24,"correct":14},"D","办理接收证书之日","本题考查的是《施工合同条件》典型条款分析。在接收证书颁发前业主确实使用了工程的任何部分的处理，该使用的部分应视为自开始使用之日起已被业主接收。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]