[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101032":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101032,779,1,"单选题","根据FIDIC《施工合同条件》，可以调整合同约定单价的条件之一是：与工程量清单中估计工程量相比，实际计量的工程量变化超过（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5%",false,{"key":16,"text":17,"correct":18},"B","10%",true,{"key":20,"text":21,"correct":14},"C","15%",{"key":23,"text":24,"correct":14},"D","20%","本题考查的是《施工合同条件》典型条款分析。当该部分工作通过计量超过工程量清单中估计工程量的数量变化超过10%时，需要调整合同约定的单价。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]