[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101031":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101031,779,1,"单选题","从开工直到颁发工程接收证书之日止的时段，工程照管的责任应由（ ）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","承包人",true,{"key":20,"text":21,"correct":14},"C","工程师",{"key":23,"text":24,"correct":14},"D","争端避免裁决委员会","本题考查的是《施工合同条件》典型条款分析。承包商应从开工日期起，承担工程照管责任，直到颁发工程接收证书之日止，程照管责任应移交给业主。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]