[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101022":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101022,779,1,"单选题","FIDIC合同系列中，《施工合同条件》中，属于工程师的主要责任和义务的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","做好项目资金安排",false,{"key":16,"text":17,"correct":14},"B","给予承包商现场占有权",{"key":19,"text":20,"correct":21},"C","确定确认合同款支付、工程变更、试验、验收等专业事项等",true,{"key":23,"text":24,"correct":14},"D","工程师还可以向助手指派任务和委托部分权力，工程师有权修改合同","2020版教材P152-153 工程师的主要责任和义务：执行业主委托的施工项目质量、进度、费用、安全、环境等目标监控和日常管理工作，包括协调、联系、指示、批准和决定等;确定确认合同款支付、工程变更、试验、验收等专业事项等;工程师还可以向助手指派任务和委托部分权力，但工程师无权修改合同，无权解除任何一方依照合同具有的职责、义务或责任。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]