[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101016":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101016,779,1,"单选题","FIDIC系列中，《施工合同条件》，工程师在收到承包商申请通知后（）天内，应向承包商颁发接收证书。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":14},"C","24",{"key":22,"text":23,"correct":24},"D","28",true,"2020版教材P153-157 工程师在收到承包商申请通知后28 天内，应向承包商颁发接收证书，注明工程或分项工程按照合同要求竣工的日期，对工程或分项工程预期使用无实质影响的少量收尾工作和缺陷(直到或当收尾工作和缺陷修补完成时)除外",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]