[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101012":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101012,779,1,"单选题","FIDI C.《施工合同条件》中，对工程量增减变化较大需要调整合同约定单价不包括的条件是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","该部分工程在合同内约定属于按单价计量支付的部分",false,{"key":16,"text":17,"correct":14},"B","该部分工作通过计量超过工程量清单中估计工程量的数量变化超过10%",{"key":19,"text":20,"correct":14},"C","计量的工作数量与工程量清单中该项单价的乘积，超过中标合同金额(我国标准合同中的“签约合同价”)的0.01%",{"key":22,"text":23,"correct":24},"D","数量的变化导致该项工作的施工单位成本变化超过2%",true,"2020版教材P153-157 1)此项工作测量的工程量比工程量表或其他报表中规定的工程量的变动超过 10%; 2) 工程量的变动与费率的乘积超过了中标合同额的 0.01%; 3) 工程量的变动直接导致该项工作每单位成本的变动超过 1%; 4) 合同中没有规定此项工作为固定费率。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]