[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101010":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101010,779,1,"单选题","（2020年真题）根据《标准设计施工总承包招标文件》中的通用合同条款，自监理入收到承包人的设计文件之日起，对承包人设计文件的审查期限应不超过（ ）日。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":21},"C","21",true,{"key":23,"text":24,"correct":14},"D","28","P127-128 承包人的设计文件提交监理人后，发包人应组织设计审查，按照发包人要求文件中约定的范围和内容审查是否满足合同要求。为了不影响后续工作，自监理人收到承包人的设计文件之日起，对承包人的设计文件审查期限不超过21 天。承包人的设计与合同约定有偏离时，应在提交设计文件的通知中予以说明。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]