[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101009":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1101009,779,1,"单选题","（2020年真题）根据《标准设计施工总承包招标文件》，关于工程分包的说法，正确的是 （ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人经发包人同意，可将全部施工分包给第三人",false,{"key":16,"text":17,"correct":14},"B","承包人的分包合同，应由分包人向监理人提交副本备案",{"key":19,"text":20,"correct":21},"C","承包人征得发包人同意，可将部分工程分包给有资质的分包人",true,{"key":23,"text":24,"correct":14},"D","发包人、监理人和承包人共同对分包人进行分包管理","P120-121 分包工作需要征得发包人同意。除发包人己同意投标文件中说明的分包外，合同履行过程中承包人还需要分包的工作，仍应征得发包人同意。承包人不得将设计和施工的主体、关键性工作的施工分包给第三人。要求承包人是具有实施工程设计和施工能力的合格主体，而非皮包公司。?分包人的资格能力应与其分包工作的标准和规模相适应，其资质能力的材料应经监理人审查。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]