[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101007":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1101007,779,1,"单选题","（2014年真题）根据《标准设计施工总承包合同》，承包人编制进度付款支付分解表时，勘察设计费分解的原则是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按提交勘察设计阶段性成果文件的时间、对应的工作量进行分解",true,{"key":16,"text":17,"correct":18},"B","按勘察设计总费用、勘察设计工作持续时间进行分解",false,{"key":20,"text":21,"correct":18},"C","按提交勘察设计阶段性成果的次数平均分解",{"key":23,"text":24,"correct":18},"D","按勘察设计总费用、项目施工周期进行分解","本题考查的是工程款支付管理。勘察设计费分类和分解原则是按照提交勘察设计阶段性成果文件的时间、对应的工作量进行分解。2020版教材P130。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]