[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101004":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1101004,779,1,"单选题","在设计施工总承包合同模式下，承包人设计文件提交监理人后，由()组织设计审查，自监理人收到设计文件起的审查期限为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","监理人，14天",false,{"key":16,"text":17,"correct":14},"B","监理人，21天",{"key":19,"text":20,"correct":14},"C","发包人，14天",{"key":22,"text":23,"correct":24},"D","发包人，21天",true,"2020版教材P127-128 承包人的设计文件提交监理人后，发包人应组织设计审查，按照发包人要求文件中约定的范围和内容审查是否满足合同要求。为了不影响后续工作，自监理人收到承包人的设计文件之日起，对承包人的设计文件审查期限不超过21天。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]