[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101000":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1101000,779,1,"单选题","关于设计施工阶段总承包合同的承包人提出合理化建议的表述中，不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","履行合同过程中，承包人可以书面形式向监理人提交改变“发包人要求”文件中有关内容的合理化建议书",false,{"key":16,"text":17,"correct":18},"B","监理人自行决定是否采纳承包人的建议",true,{"key":20,"text":21,"correct":14},"C","承包人的合理化建议被采纳并构成变更，由监理人向承包人发出变更指示",{"key":23,"text":24,"correct":14},"D","如果接受承包人提出的合理化建议，降低了合同价格、缩短了工期或者提高了工程的经济效益，发包人可依据专用条款中约定给予奖励","2020版教材P131-132 履行合同过程中，承包人可以书面形式向监理人提交改变“发包人要求”文件中有关内容的合理化建议书。监理人应与发包人协商是否采纳承包人的建议。建议被采纳并构成变更，由监理人向承包人发出变更指示。如果接受承包人提出的合理化建议，降低了合同价格、缩短了工期或者提高了工程的经济效益，发包人可依据专用条款中约定给予奖励。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]