[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100998":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100998,779,1,"单选题","符合专用条款约定的开始工作条件时，监理人获得发包人同意后应提前()天向承包人发出开始工作通知。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",true,{"key":16,"text":17,"correct":18},"B","10",false,{"key":20,"text":21,"correct":18},"C","14",{"key":23,"text":24,"correct":18},"D","21","2020版教材P127 符合专用条款约定的开始工作条件时，监理人获得发包人同意后应提前7天向承包人发出开始工作通知。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]