[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100997":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100997,779,1,"单选题","设计施工总承包合同承包人需要变动保险合同条款时，应（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","将变动结果及时通知发包人",false,{"key":16,"text":17,"correct":14},"B","事先征得发包人与监理人的同意",{"key":19,"text":20,"correct":21},"C","事先征得发包人同意，并通知监理人",true,{"key":23,"text":24,"correct":14},"D","事先征得监理人同意，并通知发包人","2020版教材P126 本题考核的是设计施工总承包保险合同条款的变动。承包人需要变动保险合同条款时，应事先征得发包人同意，并通知监理人。对于保险人做出的变动，承包人应在收到保险人通知后立即通知发包人和监理人。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]