[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100995":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100995,779,1,"单选题","关于承包人提交实施项目的计划说法错误的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承包人应按合同约定的内容和期限，编制详细的进度计划",false,{"key":16,"text":17,"correct":14},"B","监理人应在专用条款约定的期限内批复",{"key":19,"text":20,"correct":14},"C","批准的计划作为“合同进度计划”",{"key":22,"text":23,"correct":24},"D","监理人未在约定的时限内批准，计划不能实施",true,"2020版教材P127 本题考查的是承包人提交实施项目的计划。监理人未在约定的时限内批准或提出修改意见，该进度计划视为已得到批准。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]