[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100992":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100992,779,1,"单选题","在设计施工总承包合同中，下列关于分包说法不正确的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人不得将其承包的全部工程转包给第三人，也不得将其承包的全部工程肢解后以分包的名义分别转包给第三人",false,{"key":16,"text":17,"correct":14},"B","分包工作需要征得发包人同意",{"key":19,"text":20,"correct":21},"C","承包人不得将施工的主体、关键性工作的施工分包给第三人，设计工作可以全部分包",true,{"key":23,"text":24,"correct":14},"D","发包人同意分包的工作，承包人应向发包人和监理人提交分包合同副本","2020版教材P120-121 承包人不得将其承包的全部工程转包给第三人，也不得将其承包的全部工程肢解后以分包的名义分别转包给第三人。分包工作需要征得发包人同意。承包人不得将设计和施工的主体、关键性工作的施工分包给第二人。要求承包人是具有实施工程设计和施工能力的合格主体，而非皮包公司。发包人同意分包的工作，承包人应向发包人和监理人提交分包合同副本。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]