[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100991":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100991,779,1,"单选题","在设计施工总承包合同中，下列关于承包人文件的说法，错误的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","专用条款约定承包人向监理人陆续提供文件的内容、数量和时间",false,{"key":16,"text":17,"correct":14},"B","专用条款内需要约定监理人对承包人提交文件应批准的合理期限",{"key":19,"text":20,"correct":14},"C","承包人文件中最主要的是设计文件",{"key":22,"text":23,"correct":24},"D","项目实施中，监理人未在约定的期限内对提交文件提出意见，不能进行后续施工",true,"2020版教材P123-126 本题考查的是订立合同时需要明确的内容。项目实施过程中，监理人未在约定的期限内提出否定意见，视为已获批准，承包人可以继续进行后续工作 。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]