[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100983":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100983,779,1,"单选题","设计施工总承包合同模式下，承包人对总监理工程师授权的监理人员发出的指示有疑问时，可在该指示发出的()小时内向总监理工程师提出书面异议，总监理工程师应在()小时内对该指示予以确认、更改或撤销。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","12，12",false,{"key":16,"text":17,"correct":14},"B","24，24",{"key":19,"text":20,"correct":14},"C","36，36",{"key":22,"text":23,"correct":24},"D","48，48",true,"2020版教材P121 本题考查的是设计施工总承包合同管理有关各方的职责。承包人对总监理工程师授权的监理人员发出的指示有疑问时，可在该指示发出的48小时内向总监理工程师提出书面异议，总监理工程师应在48小时内对该指示予以确认、更改或撤销。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]