[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100981":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100981,779,1,"单选题","合同约定范围内的工作需国家有关部门审批时，发包人、承包人应按照合同约定的职责分工完成行政审批报送。因国家有关部门审批迟延造成费用增加和(或)工期延误，由( )承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人",false,{"key":16,"text":17,"correct":18},"B","发包人",true,{"key":20,"text":21,"correct":14},"C","政府部分",{"key":23,"text":24,"correct":14},"D","发包人和承包人","2020版教材P128-129 本题考查的是进度管理。合同约定范围内的工作需国家有关部门审批时，发包人、承包人应按照合同约定的职责分工完成行政审批报送。因国家有关部门审批迟延造成费用增加和(或)工期延误，由发包人承担 。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]