[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100976":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100976,779,1,"单选题","按照施工合同示范文本的规定，监理人接到承包人提交的进度计划后，应在合同约定的时间内予以确认或提出修改意见。如果监理人没有在约定时间内予以确认或提出修改意见，则视为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程师已经确认，承包人不再承担计划的缺陷责任",false,{"key":16,"text":17,"correct":18},"B","工程师已经确认，承包人仍应承担计划的缺陷责任",true,{"key":20,"text":21,"correct":14},"C","工程师未确认，承包人应修改进度计划",{"key":23,"text":24,"correct":14},"D","工程师未确认，承包人应等待工程师的进一步指示","2020版教材P127 本题考查的是施工准备阶段的合同管理中施工进度计划。如果监理人逾期不确认也不提出书面意见，则视为已经同意。监理人对进度计划和对承包人施工进度的认可，不免除承包人对施工组织设计和工程进度计划本身的缺陷所应承担的责任。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]