[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100973":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100973,779,1,"单选题","设计施工总承包合同模式下，不可预见物质条件的风险由发包人承担，承包人遇到不可预见物质条件时，及时通知了监理人，监理人没有发出指示，承包人因采取合理措施而增加的费用和工期延误，由（）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",true,{"key":16,"text":17,"correct":18},"B","承包人",false,{"key":20,"text":21,"correct":18},"C","监理人",{"key":23,"text":24,"correct":18},"D","发包人和承包人","2020版教材P125 本题考查的是设计施工总承包合同模式下不可预见物质条件。对于发包人承担风险的情况，承包人遇到不可预见物质条件时，应采取适应不利物质条件的合理措施继续设计和（或）施工，并及时通知监理人，通知应载明不利物质条件的内容以及承包人认为不可预见的理由。监理人收到通知后应当及时发出指示。指示构成变更的，按变更条款执行。监理人没有发出指示，承包人因采取合理措施而增加的费用和（或）工期延误，由发包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]