[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100965":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100965,779,1,"单选题","对于大型项目，竣工后试验由（ ）进行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":14},"B","承包人",{"key":19,"text":20,"correct":21},"C","发包人或承包人",true,{"key":23,"text":24,"correct":14},"D","监理人","本题考查的是竣工验收及缺陷责任期合同管理。竣工后试验按专用条款的约定由发包人或承包人进行。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]