[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100961":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100961,779,1,"单选题","在设计施工阶段不论何种原因造成工程的实际进度与合同进度计划不符时，承包人可以在专用条款约定的期限内向监理人提交修订合同进度计划的申请报告，并附有关措施和相关资料，报（ ）批准。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","监理人",true,{"key":20,"text":21,"correct":14},"C","本级建设行政主管部门",{"key":23,"text":24,"correct":14},"D","发包人与监理人共同","2020版教材P128-129 不论何种原因造成工程的实际进度与合同进度计划不符时，承包人可以在专用条款约定的期限内向监理人提交修订合同进度计划的申请报告，并附有关措施和相关资料，报监理人批准。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]