[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100954":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100954,779,1,"单选题","设计施工阶段总承包合同的承包人应提前（ ）d将申请竣工试验的通知送达监理人。并按照专用条款约定的份数，向监理人提交竣工记录、暂行操作和维修手册。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","14",false,{"key":16,"text":17,"correct":18},"B","21",true,{"key":20,"text":21,"correct":14},"C","35",{"key":23,"text":24,"correct":14},"D","42","2020版教材P136-137 承包人应提前21d将申请竣工试验的通知送达监理人，并按照专用条款约定的份数，向监理人提交竣工记录、暂行操作和维修手册。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]